The Louisiana Contract

Lubliner

Major
Forum Host
Joined
Nov 27, 2018
Location
Chattanooga, Tennessee
On September 18, 1861, E. C. Murray was awarded a contract to build a ship named Louisiana in New Orleans. The contract was for $196,000 dollars and it was to be completed by January 25, 1862. By April 19, 1862, she was still at the building wharf and was not launched until the next day, only partially completed but with most of her armament. She was sent down river to help fight the gunboats that were passing the forts south of New Orleans and eventually destroyed during the engagement.
I was interested in whether this contract was penalized by the overdue launch, and if so, what were the consequences levied against the builder? Also, the initial agreement for January 25 seems implausible even at this stage of the war. Did this contract award the full dollar amount at the beginning to build the Louisiana from scratch or were specified sums given at certain dates as the build progressed. I am aware of the sister ship Mississippi and the Tift's contract for building her being entirely different in its conception. Any help on this will be appreciated. Thanks,
Lubliner.
 
Hello Lubliner,

You have posed an interesting question that I'll try to answer but first there are some details to clarify. The Louisiana and Mississippi were not sister ships. As you've noted they were entirely different in concept, design and construction. The Mississippi was larger and built as a CSN Department project with the Tifts acting as agents of the department. Their expenses were covered but they were otherwise uncompensated. They served out of patriotism toward their new nation. The Louisiana was built by a private contractor, Murray, who was given both incentives and penalties for finishing by a certain date. It was expected that he would make a modest profit from the construction.

The Mississippi was contracted on 5 September 1861 with her keel laid on 14 October. She would be launched only on 19 April 1862 and was set afire and scuttled off New Orleans on 25 April 1862. Construction was advanced enough for launching as early as late February 1862 but she was held on the stocks waiting for the machinery to be fitted. The Louisiana was contracted on 18 September 1861 with her keel laid on 15 October. She would be launched to much fanfare on 6 February 1862 and declared commissioned and operational on 24 April 1862 after Farragut passed her and the forts earlier that morning. She too would be set afire and scuttled off the forts on 28 April 1862.

Examining the various known contracts with the actual construction dates of CSN vessels, I have yet to find a single vessel built in the contracted period. This despite the bonus incentives or penalties included in the contracts. Consider:


Ord/Cont Keel Launch Commission
Carondelet 10 Jul 14 Sept 25 Jan 16 March
Bienville 14 Sept Oct 18 Jan 4 April
Morgan 10 Jul 1 Oct 31 Jan 25 March
Gaines Sept 2 Oct 13 Feb 25 March
Mississippi 5 Sept 14 Oct 19 April -
Louisiana 18 Sept 15 Oct 6 Feb 24 April

Those were all new construction projects started in 1861 under ideal conditions. These contracts were issued with the idea that construction would proceed as it would in peacetime, albeit in a faster fashion. They did not take into account the emerging lack of supplies, the confiscation of building materials, the conscription of mechanics and carpenters, the inflationary effect of a wartime economy, and actual attacks by enemy forces. All of these factors contributed to building delays. They did not allow the builders to collect any bonuses, nor did they allow the CS government to enforce the penalty clauses of the contracts. In worse case scenarios, the CSN would lose confidence in a contractor and simply seize the vessel and attempt to complete her by themselves (e.g., Arkansas). This still did not prevent the contractor, in this case Shirley, from obtaining further contracts later.

Most CSN contracts were structured so that a builder would be paid a certain amount based upon building progress. If a builder requested a contracted payment he would have to have a CSN officer inspect the vessel and sign off on the construction before payment would be authorized. For example, Hughes was scheduled to receive his 4th and 5th payments ($10,000 each) on the gunboat Bienville on 9 and 23 November 1861. Both payments were not authorized and released until 21 December 1861. I have not yet encountered a builder paying a penalty for delayed construction, but there is documentation of builders seeking payment for work done that was never compensated. That is especially true regarding the conversion of RDF gunboats.

All the best,
Bil
 
Thank you for your answer @Bil R. Very helpful. I do realize the close proximity of both the Louisiana and the Mississippi in both time and space became a detriment especially to the latter. Other projects as well drained off workers in that area by promising better and prompter pay. This also drove up the price of timber used on the hulls of the ships. By September of 1861, I find it hard to believe the builders and the Navy Department could not foresee the usurpation of workers and materials, and the 17 weeks given to build the Mississippi sounds like an unattainable goal to begin with. She was to sport a new design that carpenters unfamiliar with ship requirements could take advantage of, allowing an increased draft of workers. But due to the new 'invention' of arming these vessels with iron, and the limited experience of that profession, it seems to me they should have been aware of the difficulties involved and given a more reliable estimation of time and expense. I believe the Tift's patriotism and desire clouded the common sense of the Department that was only six months old. I will continue exploring the enquiry by the committee of the confederate congress on the overall deficiencies that occurred in the first year of the war. Thanks again.
Lubliner.
 

Learn About Us
About CivilWarTalk
Contact the Webmaster
Meet the Staff
Link to CivilWarTalk
Join Our Community
Register
Browse Forums
View Today's Discussions
Search the Forum
Get Help
FAQ
Student Guide
Forum Rules & Etiquette
Copyright / DMCA

     Contact Us CivilwarTalk on Facebook CivilWarTalk on YouTube CivilWarTalk on Twitter RSS Feed

Bringing the American Civil War and More to Life.
© 1999 - , CIVILWARTALK, LLC - Site Version 10.0

SlaveryTalk.com - SecessionTalk.com - CivilWarTalk.com - ReconstructionTalk.com
Back
Top